Home   |   About Us   |   Accreditation   |   Case Studies   |   Videos   |   News   |   Contact Us
Product Information
Case Studies
  Ballybay Flood Defence Scheme
  Knightsbrook Hotel Foul Drainage
  NI Water septicity dosing
  River Fergus, Ennis Flood Scheme
  Newtownards Flood Relief Scheme
  Munster Blackwater Flood Drainage
  Croke Park Stormwater Pumping
Downloads
 River Fergus Ennis Flood scheme
 Holywood Wastewater pumping station
 Fermoy Phase II flood alleviation
 Drumbeg Drive WWPS detail of works
 FME packaged pump stations
 Most common pump impellers
 OXY-FLO Septicity Dosing
 Major pumping station schemes
 The portfolio of pumping stations
 Family size Pumping Substation
 TeTec Remote Pump Monitoring

Pumps and Pumping


Knightsbrook Hotel Foul Drainage
   
Client:
Completion date:
Contract Value:
Cusack Homes
1996
56,0000 excl. civil works
   
Project Overview:

Design supply and construction of a 10m deep precast concrete foul water pumping station with 24 hours overflow storage, representing one of FM Environmentals' deepest turnkey installations.

FM Environmental was engaged by Consulting Engineers, Erneview Consultants to design, tender and build a pumping station that could provide 24 hours emergency storage to serve the newly constructed hotel in Trim, ireland. This project faced the additional challenge of having an invert level four and half meters below finished ground, whilst not allowing the wastewaters to return back up the rising main.

Delivered in partnership with a civil works main contractor, The dig required a 10 metre excavation, however using precast concrete pump chambers, the project was completed on time and on budget with minimal problems for the main contractor. With a strong focus on Health & Safety, the project was delivered to the client within an 9 week period from date of contract award.

Our scope of supply is highlighted within the attached drawing.

   
Scope Of Work:

The scheme consisted of submersible pumps (duty/standby) capable of delivery flows of 12 litres/second, 10m precast pump chamber, precast concrete overflow tank, internal pipework and guiderails, external valves arrangements, control panel with ammeters, hours run meters, telemetry, high level alarm, GRP Kiosk. Access covers complete with anti-fall arrest system. lifting equipment.

FM Environmental successfully services this pumping station to this day.

   
 








address: Greenbank Industrial Estate, Newry, BT34 2QX, N. Ireland
      
tel: +44(0) 28 302 66616 email: sales@fmenvironmental.com
  © 2012 FM Environmental Limited. All Rights Reserved.
             

Designed By Eweb